Barrow Solar Farm
Barrow Solar Farm, OPDE UK Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 29.6 MW, grid supply point Bramford.
- Customer
- OPDE UK Limited
- Status
- Accepted to connect
- Capacity
- 29.6 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Bramford
- Bulk supply point
- Bury Grid 33kV
- Point of connection
- Barrow Primary
- Voltage
- 33 kV
- Date accepted
- 8 Apr 2026
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Aug 2026
- Licence area
- EPN
- Address
- Mill Lane, Bury St Edmunds
- Postcode
- IP29 5BT
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.