Grid GuardianOpen the evidence in the app

Barrow Solar Farm

Barrow Solar Farm, OPDE UK Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 29.6 MW, grid supply point Bramford.

Customer
OPDE UK Limited
Status
Accepted to connect
Capacity
29.6 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bramford
Bulk supply point
Bury Grid 33kV
Point of connection
Barrow Primary
Voltage
33 kV
Date accepted
8 Apr 2026
In a connection queue
Yes
Row last updated by the DNO
14 Aug 2026
Licence area
EPN
Address
Mill Lane, Bury St Edmunds
Postcode
IP29 5BT

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source