Grid GuardianOpen the evidence in the app

Bank Farm Solar

Bank Farm Solar, Skyfall Energy Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 99.9 MW, grid supply point Sellindge.

Customer
Skyfall Energy Limited
Status
Accepted to connect
Capacity
99.9 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
Yes (capacity not firm)
Grid supply point
Sellindge
Voltage
132 kV
Date accepted
15 Apr 2020
Target energisation
31 Jan 2025
In a connection queue
Yes
Row last updated by the DNO
14 Jun 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Bank Road, Ashford
Postcode
TN25 7DF

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source