Ardleigh Solar Farm

Ardleigh Solar Farm, Solarfields Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Bramford.

Customer
Solarfields Limited
Status
Connected
Capacity
20 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Bramford
Bulk supply point
Lawford Grid 33kV
Voltage
33 kV
Date connected
24 Mar 2016
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Off Park Road, Ardleigh
Postcode
CO7 7SS
Export MPAN
1050001061602

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.