(ANM) Weirs Drove 2
(ANM) Weirs Drove 2, Anesco Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 30 MW, grid supply point Burwell.
- Customer
- Anesco Limited
- Status
- Accepted to connect
- Capacity
- 30 MW
- Technology
- Storage (Storage - Electrochemical (Batteries))
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Burwell
- Voltage
- 132 kV
- Date accepted
- 27 Aug 2020
- Target energisation
- 31 Oct 2028
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Dec 2022
- Licence area
- EPN
- Address
- Cambridge
- Postcode
- CB25 0BP
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.