(ANM) Redisham Hall Farm

(ANM) Redisham Hall Farm, OPDE UK Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 29.63 MW, grid supply point Bramford.

Customer
OPDE UK Limited
Status
Accepted to connect
Capacity
29.63 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bramford
Bulk supply point
Ilketshall Grid 33kV
Voltage
33 kV
Date accepted
12 Aug 2023
Target energisation
31 Oct 2034
In a connection queue
Yes
Row last updated by the DNO
15 Apr 2024
Licence area
EPN
Address
School Road, Beccles
Postcode
NR34 8NY

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.