(ANM) Minos Solar Farm
(ANM) Minos Solar Farm, Low Carbon Solar Park 27 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Bramford.
- Customer
- Low Carbon Solar Park 27 Limited
- Status
- Accepted to connect
- Capacity
- 20 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Bramford
- Bulk supply point
- Stowmarket Grid 33kV
- Voltage
- 33 kV
- Date accepted
- 30 Jun 2021
- Target energisation
- 31 Oct 2031
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Dec 2022
- Licence area
- EPN
- Address
- Stowmarket
- Postcode
- IP14 5BL
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.