(ANM) Low Fen Drove Way
(ANM) Low Fen Drove Way, Fen Ditton Solar And Battery Storage Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.9 MW, grid supply point Burwell.
- Customer
- Fen Ditton Solar And Battery Storage Limited
- Status
- Accepted to connect
- Capacity
- 49.9 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Burwell
- Voltage
- 132 kV
- Date accepted
- 26 Aug 2021
- Target energisation
- 31 Oct 2031
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Dec 2022
- Licence area
- EPN
- Address
- Fen Ditton, Horningsea
- Postcode
- CB25 9AT
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.