(ANM) Land North Of Jack'S Lane

(ANM) Land North Of Jack'S Lane, Padero Solaer Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20.2 MW, grid supply point Bramford.

Customer
Padero Solaer Limited
Status
Accepted to connect
Capacity
20.2 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bramford
Bulk supply point
Stowmarket Grid 132/33kV
Voltage
33 kV
Date accepted
13 Aug 2025
In a connection queue
Yes
Row last updated by the DNO
12 Sept 2025
Licence area
EPN
Address
Combs, Stowmarket
Postcode
IP14 2NG

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.