(ANM) Land North Of A143

(ANM) Land North Of A143, PS Renewables, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 48 MW, grid supply point Bramford.

Customer
PS Renewables
Status
Accepted to connect
Capacity
48 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bramford
Voltage
132 kV
Date accepted
3 Feb 2021
Target energisation
31 Dec 2028
In a connection queue
Yes
Row last updated by the DNO
14 Dec 2022
Licence area
EPN
Address
Diss
Postcode
IP22 1AZ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.