(ANM) Land At Sewardstone Road

(ANM) Land At Sewardstone Road, Intelligent Alternatives, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 99.9 MW, grid supply point Brimsdown (EPN).

Customer
Intelligent Alternatives
Status
Accepted to connect
Capacity
99.9 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Brimsdown (EPN)
Voltage
132 kV
Date accepted
21 Jun 2023
Target energisation
31 Oct 2033
In a connection queue
Yes
Row last updated by the DNO
15 Jan 2024
Licence area
EPN
Address
Sewardstone Road, Waltham Abbey
Postcode
EN9 3QH

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.