Grid GuardianOpen the evidence in the app

(ANM) Green End

(ANM) Green End, Renewable Connections Developments Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 25 MW, grid supply point Burwell.

Customer
Renewable Connections Developments Limited
Status
Accepted to connect
Capacity
25 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Burwell
Bulk supply point
Histon Grid 132/33kV
Point of connection
Landbeach SW/STN 33kV
Voltage
33 kV
Date accepted
6 Mar 2025
In a connection queue
Yes
Row last updated by the DNO
14 Jul 2025
Licence area
EPN
Address
Landbeach, Cambridge
Postcode
CB25 9FD

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source