Grid GuardianOpen the evidence in the app

(ANM) Exning Farm

(ANM) Exning Farm, Vantage RE Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 24 MW, grid supply point Burwell.

Customer
Vantage RE Limited
Status
Accepted to connect
Capacity
24 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Burwell
Bulk supply point
Burwell Local Grid 132/33kV
Point of connection
Exning Solar Park 33kV
Voltage
33 kV
Date accepted
18 Jul 2025
In a connection queue
Yes
Row last updated by the DNO
14 Aug 2025
Licence area
EPN
Address
Newmarket
Postcode
CB8 0XG

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source