Grid GuardianOpen the evidence in the app

(ANM) Epping Solar Farm

(ANM) Epping Solar Farm, Low Carbon Solar Park 46 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 35 MW, grid supply point Rye House.

Customer
Low Carbon Solar Park 46 Limited
Status
Accepted to connect
Capacity
35 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Rye House
Bulk supply point
Epping Grid 33kV
Voltage
33 kV
Date accepted
11 Jun 2023
Target energisation
31 Oct 2034
In a connection queue
Yes
Row last updated by the DNO
12 Jul 2024
Licence area
EPN
Address
Lindsey Street, Epping
Postcode
CM16 6RD

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source