(ANM) Crabbes Farm

(ANM) Crabbes Farm, B17 Solar Farm Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 35 MW, grid supply point Bramford.

Customer
B17 Solar Farm Limited
Status
Accepted to connect
Capacity
35 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bramford
Bulk supply point
Wickham Market Grid 33kV
Voltage
33 kV
Date accepted
21 Aug 2020
Target energisation
31 Dec 2028
In a connection queue
Yes
Row last updated by the DNO
14 Dec 2022
Licence area
EPN
Address
Woodbridge
Postcode
IP13 9AD

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.