(ANM) Clay Lane

(ANM) Clay Lane, Clay Lane Solar Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Bramford.

Customer
Clay Lane Solar Limited
Status
Accepted to connect
Capacity
20 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bramford
Bulk supply point
Clacton Grid 33kV
Voltage
33 kV
Date accepted
26 May 2021
Target energisation
31 Oct 2031
In a connection queue
Yes
Row last updated by the DNO
13 Sept 2024
Licence area
EPN
Address
Clacton On Sea
Postcode
CO16 8HG

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.