(ANM) Chediston Hall
(ANM) Chediston Hall, Sky UK Development Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 40 MW, grid supply point Bramford.
- Customer
- Sky UK Development Limited
- Status
- Accepted to connect
- Capacity
- 40 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Bramford
- Bulk supply point
- Halesworth Grid 33kV
- Voltage
- 33 kV
- Date accepted
- 21 Apr 2023
- Target energisation
- 31 Oct 2034
- In a connection queue
- Yes
- Row last updated by the DNO
- 15 Jan 2024
- Licence area
- EPN
- Address
- Chediston, Halesworth
- Postcode
- IP19 0AW
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.