Grid GuardianOpen the evidence in the app

(ANM) Brick Lane

(ANM) Brick Lane, QC Otranto Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 50 MW, grid supply point Bramford.

Customer
QC Otranto Limited
Status
Accepted to connect
Capacity
50 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bramford
Bulk supply point
Wickham Market Grid 132/33kV
Voltage
132 kV
Date accepted
31 Dec 2024
In a connection queue
Yes
Row last updated by the DNO
14 Feb 2025
Licence area
EPN
Address
Woodbridge
Postcode
IP13 9LG

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source