Grid GuardianOpen the evidence in the app

(ANM) Barleylands Road

(ANM) Barleylands Road, Anglo Renewables Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.9 MW, grid supply point Tilbury.

Customer
Anglo Renewables Limited
Status
Accepted to connect
Capacity
49.9 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
Yes (capacity not firm)
Grid supply point
Tilbury
Voltage
132 kV
Date accepted
17 May 2021
Target energisation
30 Oct 2030
In a connection queue
Yes
Row last updated by the DNO
13 Oct 2023
Licence area
EPN
Address
Basildon
Postcode
SS15 4BG

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source