(ANM) Bardwell Fields Farm

(ANM) Bardwell Fields Farm, OPDE UK Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 29.63 MW, grid supply point Bramford.

Customer
OPDE UK Limited
Status
Accepted to connect
Capacity
29.63 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bramford
Bulk supply point
Diss Grid 33kV
Point of connection
Stanton Primary 11kV
Voltage
33 kV
Date accepted
12 Apr 2023
Target energisation
31 Oct 2034
In a connection queue
Yes
Row last updated by the DNO
15 Apr 2024
Licence area
EPN
Address
Bury St Edmunds
Postcode
IP31 1AQ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.