Grid GuardianOpen the evidence in the app

Allington Generation

Allington Generation, Kent Enviropower, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 40 MW, grid supply point Canterbury.

Customer
Kent Enviropower
Status
Connected
Capacity
40 MW
Maximum import capacity
32.3 MW
Technology
Energy from waste (Steam turbine (thermal power plant))
Flexible connection
No
Grid supply point
Canterbury
Bulk supply point
Maidstone Grid 33kV
Voltage
33 kV
Date connected
27 Oct 2005
In a connection queue
No
Row last updated by the DNO
14 Dec 2022
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Laverstoke Road, Maidstone
Postcode
ME16 0LE
Export MPAN
1900070394466

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source