Grid GuardianOpen the evidence in the app

5 North Colonnade

5 North Colonnade, Barclays Capital, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4.4 MW, grid supply point West Ham.

Customer
Barclays Capital
Status
Connected
Capacity
4.4 MW
Technology
Fossil - Oil (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
West Ham
Point of connection
Simpsons Road 11kV
Voltage
11 kV
Date connected
18 Aug 2015
In a connection queue
No
Row last updated by the DNO
14 Dec 2021
Licence area
London Power Networks plc
Address
Poplar
Postcode
E14 4BB

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source