Whitelaw Brae BESS 33kV substation

Whitelaw Brae BESS 33kV substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 1 MW in the queue, 1 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
1 MW
Gate 2 MW
1 MW
MW connected
0 MW
Earliest confirmed date
31 Jul 2026

By technology

TechnologyProjectsMW
Storage11

Projects at Whitelaw Brae BESS 33kV substation

ProjectTechnologyMWGateStatusMW effective from
Whitelaw Brae BESSStorage1Gate 2Under Construction/Commissioning31 Jul 2026

Source