Whitelaw Brae 'A' and 'B' 33kV Substations

Whitelaw Brae 'A' and 'B' 33kV Substations (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 57 MW in the queue, 57 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
57 MW
Gate 2 MW
57 MW
MW connected
0 MW
Earliest confirmed date
31 Jul 2026

By technology

TechnologyProjectsMW
Onshore wind157

Projects at Whitelaw Brae 'A' and 'B' 33kV Substations

ProjectTechnologyMWGateStatusMW effective from
Whitelaw Brae WindfarmOnshore wind57Gate 2Under Construction/Commissioning31 Jul 2026