Grid GuardianOpen this site in the app

Whitburn 400kV substation

Whitburn 400kV substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 280 MW in the queue, 280 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
280 MW
Gate 1 MW
280 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage1280

Projects at Whitburn 400kV substation

ProjectTechnologyMWGateStatusMW effective from
Alcemi Armadale BESSStorage280Gate 1Scoping31 Oct 2030

Source