West Country Connection Node E 400kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 480 MW in the queue, 480 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
Transmission owner
NGET
Projects
1
MW in the queue
480 MW
Gate 1 MW
480 MW
MW connected
0 MW
By technology
Technology
Projects
MW
Solar
1
480
Storage
1
480
Projects at West Country Connection Node E 400kV Substation