Grid GuardianOpen this site in the app

West Country Connection Node C 400kV Substation

West Country Connection Node C 400kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 1,200 MW in the queue, 1,200 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
1,200 MW
Gate 1 MW
1,200 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Solar11,200
Storage11,200

Projects at West Country Connection Node C 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
The BeaconStorage, Solar1,200Gate 1Scoping31 Oct 2037

Source