West Anglia Connection Node F 400kV Substation

West Anglia Connection Node F 400kV Substation (NGET) has 6 projects in NESO's TEC Register of 23 Oct 2026: 3,429 MW in the queue, 1,729 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
6
MW in the queue
3,429 MW
Gate 1 MW
1,729 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Solar63,429
Storage52,429
Demand21,700
Hydro11,000
Nuclear11,000
Onshore wind11,000
Reactive Compensation1700

Projects at West Anglia Connection Node F 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Little HarrowdenDemand, Solar1,000Scoping31 Oct 2034
Market Harborough Green Energy HubStorage, Hydro, Nuclear, Solar, Onshore wind1,000Gate 1Scoping31 Oct 2034
Market HarboroughDemand, Storage, Solar, Reactive Compensation700Awaiting Consents31 Oct 2034
Noventum Market HarboroughStorage, Solar249Gate 1Scoping31 Oct 2034
Lightsource BraybrookeStorage, Solar240Gate 1Scoping31 Oct 2034
Nethercourt Solar & BESS FarmStorage, Solar240Gate 1Scoping31 Oct 2034