Grid GuardianOpen this site in the app

Wearside Connection Node B 400kV Substation

Wearside Connection Node B 400kV Substation (NGET) has 5 projects in NESO's TEC Register of 23 Oct 2026: 1,797 MW in the queue, 797 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
5
MW in the queue
1,797 MW
Gate 1 MW
797 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage51,797
Solar2297

Projects at Wearside Connection Node B 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
NatPower Hawthorn Pit Green Energy ParkStorage1,000Scoping30 Oct 2035
Zenobe Hawthorn Pit BESSStorage300Gate 1Scoping30 Oct 2035
Lightsource Hawthorne PitStorage, Solar240Gate 1Scoping30 Oct 2035
Hawthorn BESSStorage200Gate 1Awaiting Consents30 Oct 2035
Noventum Hawthorn PitStorage, Solar57Gate 1Scoping30 Oct 2035

Source