Waltham Cross B 400kV Substation

Waltham Cross B 400kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 249.9 MW in the queue, 249.9 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
249.9 MW
Gate 1 MW
249.9 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Solar1249.9
Storage1249.9

Projects at Waltham Cross B 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Waltham Cross PV & BESS SubStorage, Solar249.9Gate 1Scoping31 Oct 2029