Grid GuardianOpen this site in the app

Vale of Leven 132kV substation

Vale of Leven 132kV substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 72 MW in the queue, 72 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
72 MW
Gate 1 MW
72 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind172

Projects at Vale of Leven 132kV substation

ProjectTechnologyMWGateStatusMW effective from
Vale of Leven Wind FarmOnshore wind72Gate 1Scoping31 Oct 2033

Source