Tynemouth 275kV Substation

Tynemouth 275kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 70 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
70 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage170

Projects at Tynemouth 275kV Substation

ProjectTechnologyMWGateStatusMW effective from
Don CossackStorage70Awaiting Consents15 Jun 2034