Grid GuardianOpen this site in the app

Tilbury 132kV Substation

Tilbury 132kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, 750 MW of it Gate 2, and 793 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
0 MW
Gate 2 MW
750 MW
MW connected
793 MW

By technology

TechnologyProjectsMW
Gas1750
Storage1750
Bioenergy143

Projects at Tilbury 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Thurrock Power StationStorage, Gas300–750Gate 2Built30 Jun 2026
TilburyBioenergy43Built

Source