Thurso South 275kV Substation
Thurso South 275kV Substation (SHET) has 5 projects in NESO's TEC Register of 23 Oct 2026: 936 MW in the queue, 700 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 5
- MW in the queue
- 936 MW
- Gate 1 MW
- 700 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 4 | 900 |
| Solar | 1 | 200 |
| Onshore wind | 1 | 36 |
Projects at Thurso South 275kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Mybster 2 Battery Storage | Storage | 500 | Gate 1 | Scoping | 31 Oct 2034 |
| Lythmore | Storage, Solar | 200 | Scoping | 31 Oct 2034 | |
| Farm 100MW BESS | Storage | 100 | Gate 1 | Scoping | 31 Oct 2033 |
| Thurso South BESS | Storage | 100 | Gate 1 | Scoping | 31 Oct 2030 |
| Cairnmore Hill Wind Farm | Onshore wind | 36 | Awaiting Consents | 31 May 2028 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.