Thormanby 400kV Substation

Thormanby 400kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 599.9 MW in the queue, 599.9 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
599.9 MW
Gate 1 MW
599.9 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Solar2599.9
Storage2599.9

Projects at Thormanby 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Sedgeby Solar FarmStorage, Solar350Gate 1Awaiting Consents28 Oct 2033
Poppleton PV & BESS SubStorage, Solar249.9Gate 1Scoping24 Oct 2035