Grid GuardianRequest access to Grid Guardian

Taynuilt 132/33kV GSP Substation

Taynuilt 132/33kV GSP Substation (SHET) has 1 project in NESO's TEC Register of 13 Nov 2026: 35 MW in the queue, 35 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
35 MW
Gate 2 MW
35 MW
MW connected
0 MW
Earliest confirmed date
28 Mar 2031

By technology

TechnologyProjectsMW
Onshore wind135

Projects at Taynuilt 132/33kV GSP Substation

ProjectTechnologyMWGateStatusMW effective from
Beinn GhlasOnshore wind35Gate 2Consents Approved28 Mar 2031

Source