Grid GuardianOpen this site in the app

Sundon 400kV Substation

Sundon 400kV Substation (NGET) has 7 projects in NESO's TEC Register of 23 Oct 2026: 1,150 MW in the queue, 50 MW of it Gate 2, 500 MW Gate 1, and 179.3 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
7
MW in the queue
1,150 MW
Gate 2 MW
50 MW
Gate 1 MW
500 MW
MW connected
179.3 MW
Earliest confirmed date
30 Apr 2027

By technology

TechnologyProjectsMW
Storage61,279
Solar149.9

Projects at Sundon 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
FancottStorage600Scoping30 Oct 2031
Sundon StorageStorage500Gate 1Scoping30 Oct 2027
SundonStorage50Gate 2Under Construction/Commissioning30 Apr 2027
Sundon Pivoted PowerSolar49.9Built
Chapel Farm Battery Storage ProjectStorage49.5Built
Clayhill FarmStorage40Built
SundonStorage39.9Built

Source