Strathy North 132/33kV Substation

Strathy North 132/33kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 67.65 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
0 MW
MW connected
67.65 MW

By technology

TechnologyProjectsMW
Onshore wind167.65

Projects at Strathy North 132/33kV Substation

ProjectTechnologyMWGateStatusMW effective from
Strathy North WindOnshore wind67.65Built