Grid GuardianOpen this site in the app

Stocksbridge 400kV Substation

Stocksbridge 400kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 249 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
249 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Demand1249
Solar1249
Storage1249

Projects at Stocksbridge 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
EcoStocksbridgeDemand, Storage, Solar249Scoping30 Oct 2036

Source