Staffordshire Connection Node D 132kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 299.6 MW in the queue, 299.6 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
Transmission owner
NGET
Projects
2
MW in the queue
299.6 MW
Gate 1 MW
299.6 MW
MW connected
0 MW
By technology
Technology
Projects
MW
Solar
2
299.6
Storage
2
299.6