SPT Margree collector substation

SPT Margree collector substation (SPT) has 3 projects in NESO's TEC Register of 23 Oct 2026: 145 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
3
MW in the queue
145 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind3145

Projects at SPT Margree collector substation

ProjectTechnologyMWGateStatusMW effective from
Fell Wind FarmOnshore wind50Scoping31 Oct 2029
Margree Wind FarmOnshore wind50Awaiting Consents31 Oct 2029
Glenshimmeroch WindfarmOnshore wind45Consents Approved31 Oct 2029