SPT Margree collector substation
SPT Margree collector substation (SPT) has 3 projects in NESO's TEC Register of 23 Oct 2026: 145 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 3
- MW in the queue
- 145 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 3 | 145 |
Projects at SPT Margree collector substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Fell Wind Farm | Onshore wind | 50 | Scoping | 31 Oct 2029 | |
| Margree Wind Farm | Onshore wind | 50 | Awaiting Consents | 31 Oct 2029 | |
| Glenshimmeroch Windfarm | Onshore wind | 45 | Consents Approved | 31 Oct 2029 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.