Spittal 132kV Substation

Spittal 132kV Substation (SHET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 1,062 MW in the queue, 900 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
3
MW in the queue
1,062 MW
Gate 1 MW
900 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage31,062
Solar2762

Projects at Spittal 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
SSE Spittal Energy ParkStorage, Solar600Gate 1Scoping31 Oct 2033
Spittal BESSStorage300Gate 1Scoping31 Oct 2030
Balvedavist 162 Battery StorageStorage, Solar162Awaiting Consents31 Oct 2030