Grid GuardianOpen this site in the app

South Anglia Connection Node B 400kV Substation

South Anglia Connection Node B 400kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 1,420 MW in the queue, 1,420 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
3
MW in the queue
1,420 MW
Gate 1 MW
1,420 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Solar31,420
Storage31,420

Projects at South Anglia Connection Node B 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Great Oak SolarStorage, Solar700Gate 1Scoping31 Oct 2034
Butlers Energy ProjectStorage, Solar480Gate 1Scoping31 Oct 2034
Butlers Wood PV & BESS StationStorage, Solar240Gate 1Scoping31 Oct 2034

Source