South Anglia Connection Node A 400kV Substation

South Anglia Connection Node A 400kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 1,240 MW in the queue, 1,240 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
1,240 MW
Gate 1 MW
1,240 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage21,240
Solar1240

Projects at South Anglia Connection Node A 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Alcemi Bramford Battery Energy Storage Facility Phase 2Storage1,000Gate 1Scoping31 Oct 2034
Lightsource Bramford PV & BESSStorage, Solar240Gate 1Scoping30 Oct 2034