Solent Connection Node B 132kV Substation

Solent Connection Node B 132kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 120 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
120 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage1120

Projects at Solent Connection Node B 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Pigeon House BESSStorage120Scoping30 Oct 2037

Source