Grid GuardianOpen this site in the app

Slickly Wind Farm 132kV Substation

Slickly Wind Farm 132kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 114 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
114 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind1114
Storage1114

Projects at Slickly Wind Farm 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Slickly Wind FarmStorage, Onshore wind114Consents Approved12 Dec 2029

Source