Scatsta 132kV Substation
Scatsta 132kV Substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 54.9 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 2
- MW in the queue
- 54.9 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 2 | 54.9 |
| Demand | 1 | 49.9 |
Projects at Scatsta 132kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Scatsta Greener Grid Park | Demand, Storage | 49.9 | Scoping | 31 Oct 2028 | |
| Scatsta1 Greener Grid Park | Storage | 5 | Scoping | 31 Oct 2028 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.