ROWANCRAIG WIND FARM 33KV SUBSTATION (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 40 MW in the queue, 40 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
40 MW
Gate 1 MW
40 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind140

Projects at ROWANCRAIG WIND FARM 33KV SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Rowancraig Wind FarmOnshore wind40Gate 1Scoping31 May 2030