Grid GuardianOpen this site in the app

REDSHAW 132kV B BOARD SUBSTATION

REDSHAW 132kV B BOARD SUBSTATION (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 108 MW in the queue, 108 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
108 MW
Gate 1 MW
108 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind1108

Projects at REDSHAW 132kV B BOARD SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Grayside Wind FarmOnshore wind108Gate 1Scoping31 Oct 2037

Source