Rayleigh Main 400kV Substation

Rayleigh Main 400kV Substation (NGET) has 6 projects in NESO's TEC Register of 23 Oct 2026: 513.8 MW in the queue, 150 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
6
MW in the queue
513.8 MW
Gate 1 MW
150 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage5393.8
Onshore wind1120
Solar2114

Projects at Rayleigh Main 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Fairgreen Energy StorageStorage150Gate 1Scoping31 Oct 2034
Middlewick WindOnshore wind120Scoping31 Oct 2034
Dollymans StorageStorage99.8Scoping12 Jan 2023
Rayleigh 1 TertiaryStorage, Solar57Consents Approved31 Oct 2028
Rayleigh 2 TertiaryStorage, Solar57Scoping31 Oct 2028
Rayleigh GP3Storage30Scoping30 Oct 2034