Rassau 400kV Substation
Rassau 400kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 565 MW in the queue, 400 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 3
- MW in the queue
- 565 MW
- Gate 1 MW
- 400 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 2 | 565 |
| Solar | 2 | 565 |
| Storage | 2 | 565 |
| Reactive Compensation | 1 | 0 |
Projects at Rassau 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Rassau | Storage, Solar, Onshore wind | 400 | Gate 1 | Scoping | 31 Oct 2030 |
| Banc y Celyn Energy Park | Storage, Solar, Onshore wind | 165 | Scoping | 31 Oct 2037 | |
| Rassau Stability Services Limited | Reactive Compensation | 0 | Scoping | 31 Oct 2037 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.